Demolitions are now complete. Excavations have commenced, we have hit a problem due to all the rain recently.
The water table is only 1m below ground level, whereas it was at nearly 3m a year ago.
We have had to install a de-watering Plant which sucks the water out of the ground and pumps it away.
The Plant runs 24 hours a day and will allow excavation and concreting.
We have now excavated 75m of trenches, 3 lines of 25m long down to approx 1.5m.
These will form 3 of the 4 foundations which will carry the walls supporting the Precast concrete floor beams.
The fourth foundation will utilise the foundation already in from 1986.
The foundations will be concreted on Friday.
The bricklayers are due starting the Tuesday after the bank holiday.
The new Precast Concrete beams are due w/c 14th, 30% of the floor will use Precast beams salvaged from the demolition.
David
David Pick
David.pick@outlook.com or telephone 07713644668.
PHASE 1
http://alturl.com/t8ofu
PHASE 2
PHASE 3
http://alturl.com/obxdp
--------------------------------------------
HAVE YOU VOLUNTEERED TO HELP AT THE NEWARK & NOTTINGHAMSHIRE COUNTY SHOW
IF NOT PLEASE DO IT NOW
FOR MORE DETAILS GO TO:- NEWARK SHOW
------------------------------------------------------------
ARE YOU A MEMBER OF THE CLUBS OFFICIAL WEB SITE?
KEEPING UPDATED WITH ALL THINGS RUGBY AT NEWARK
IF NOT SELECT “HOW TO JOIN” TO FIND OUT MORE
YOU CAN STILL HAVE A LITTLE TIME LEFT TO DONATE TO OBTAIN A SPECIAL BRICK
THAT WILL BE PART OF THE NEW CLUB HOUSE
SELECT “DONATE A BRICK” FOR MORE INFORMATION
---------------------------------------------------------
CAN YOU HELP – RAISE THE BAR
GO TO THE FOLLOWING LINK TO FIND OUT MORE
If you have any ideas of ways to help us please contact our president -'president@newarkrugby.com' who will be pleased to hear from you.
------------
.
.
.
.
.
.