23-02-2017 CLUB REDEVELOPMENT PROGRESS – UPDATE

23-02-2017 CLUB REDEVELOPMENT PROGRESS – UPDATE

Newark - ADMIN ONLY RUFC - WEB SITE23 Feb 2017 - 11:07
Share via
FacebookTwitter
https://www.newarkrugby.com/ne

The latest update


Precast Concrete Floor is starting to go in to the Bay Grid 1 to 2 (closest to the First team pitch).

It consists of 225mm thick Precast Concrete Beams (an inverted T section) with Blockwork in fill between which will have 75mm insulation placed on top and then a 75mm reinforced Concrete Screed.

David

David Pick

The Photo archive has been updated

Go to the following link to view the photo archive

http://alturl.com/t8ofu

-----------------------------
TO COMPLETE THE WHOLE BUILDING PROJECT WE STILL NEED TO RAISE FUNDING