27-03-2017 CLUB REDEVELOPMENT PROGRESS – UPDATE

27-03-2017 CLUB REDEVELOPMENT PROGRESS – UPDATE

Newark - ADMIN ONLY RUFC - WEB SITE27 Mar 2017 - 11:01
Share via
FacebookTwitter
https://www.newarkrugby.com/ne

The latest update


The insulation and reinforcement is being placed on the precast floor ready for concrete to be poured on Wednesday, when cured this will allow us to build the internal walls and partitions to form the referees and team changing rooms and sundry other rooms of phase 1.

The Tuesday team of club members have now completely removed the old roof structure of the timber clubhouse, the timber has been de-nailed and cleaned and will be re-used where we can or sold.

The roofing work continues, although it has been hampered slightly by the weather, we have approximately 90% of the roof sheeting fixed and insulated. The contractor will then commence the side sheeting.

The new Electrical room has been formed internally and the new incoming mains cabinet has been fixed on the outside of the building. The new electrical supply will be connected this week by Western Power Distribution and when completed Gladwin Electrical will make the change over of the floodlight supplies feeding the 17 floodlights we have on site.

David

David Pick

The Photo archive has been updated

Go to the following link to view the photo archive

http://alturl.com/t8ofu

-----------------------------

TO COMPLETE THE WHOLE BUILDING PROJECT WE STILL NEED TO RAISE FUNDING

CAN YOU HELP - WHY NOT DONATE A BRICK

GO TO THE FOLLOWING LINK TO FIND OUT MORE

http://alturl.com/kx4ms