ON TARGET
All the walls, both internal and external for phase 3 are complete in 2 weeks.
The services team are in first fixing heating and electrical works, the plastering and joiners start w/c 9th July and the suspended ceilings and floor finishes will follow on.
We are on programme for a mid-September completion.
David
David Pick
David.pick@outlook.com or telephone 07713644668.
PHASE 1
http://alturl.com/t8ofu
PHASE 2
PHASE 3
http://alturl.com/obxdp