29/150
Share via
FacebookTwitter
https://www.newarkrugby.com/ph
20-09-2016 Today we completed the removal of the existing floor beams in the area of the rear fire escape and Physio room, the area that will form the new plant room for Phase 1, work carried out by David Pick assisted by Andrew Clay, Tom Hinchcliffe, Ter
20-09-2016 Today we completed the removal of the existing floor beams in the area of the rear fire escape and Physio room, the area that will form the new plant room for Phase 1, work carried out by David Pick assisted by Andrew Clay, Tom Hinchcliffe, Ter