Progress is good.
Progress update.
The temporary stud wall between Phases 2 and 3 is removed and the blockwork exposed.
The blockwork will be plastered in 2 weeks. The Joiners are back on site making abs fixing door abs window frames.
The Tuesday Team have been busy painting miles of Shiplap boarding before it is fixed in 2 weeks.
The Roofers will finish the Phase 3 roof up to the gable end today.
The Steel for the Road end entrance lobby, toilets and store room extension arrives Monday.
First fix Plumbing and Electrics will be finished next week.
The plasters will be on site next week followed by the suspended Ceiling team.
Most importantly the Bar is ordered for delivery and installation late August. The furniture is also ordered, as is the Kitchen equipment.
David
David Pick
David.pick@outlook.com or telephone 07713644668.
PHASE 1
http://alturl.com/t8ofu
PHASE 2
PHASE 3
http://alturl.com/obxdp
THE NEW SEASON WILL SOON BE HERE
IT IS IMPORTANT THAT THE CLUB CAN KEEP YOU UPDATED ON WHAT’S HAPPENING
HAVE YOU CHANGED YOUR EMAIL ADDRESS?
HAVE YOU CHECKED THAT YOUR EMAIL ADDRESS IS CORRECT ON THE CLUBS WEB SITE?
To change your Website email address, you need to follow the instructions in the following link
ARE YOU A MEMBER OF THE CLUBS OFFICIAL WEB SITE?
KEEPING UPDATED WITH ALL THINGS RUGBY AT NEWARK
IF NOT SELECT “HOW TO JOIN” TO FIND OUT MORE
------------
.
.
.
.
.
.