Phase 2 Progress

Phase 2

The work on Phase 2 continues

Work on Phase 2 progresses well.

All services (Electrics and Plumbing) are first fixed, the Ceiling grid in place, services second fix starts from Thursday, floor finishing programmed for w/c 27th, painting final coats from 4th December heading for completion by Friday 15th.

This week we have been braking out the concrete steps, terracing and handrails to form the new entrance to phase 2.

The steps were the old changing room players entrance, they will be replaced with a wide set of steel steps and a landing with a new accessible viewing area for wheelchairs.

The new access steps are being manufacture and these will eventually be the entrance to the clubhouse from pitch 1 side.

A separate rear entrance is also being manufactured to allow a rear fire exit, access door to pitch 2 side with an inbuilt high level viewing platform.

David

David Pick
David.pick@outlook.com or telephone 07713644668.

The Photo archive has been updated

Go to the following links to view the photo archive

PHASE 1

http://alturl.com/t8ofu

PHASE 2

http://alturl.com/xujre

HAVE YOU VOTED IN THE AVIVA COMPETITION?

IF NOT PLEASE DO SO ASAP

GO TO THE FOLLOWING LINK TO FIND OUT HOW

DIRECT LINK to the project = http://bit.ly/2znKV4M
YOUR VOTE IS IMPORTANT

-------------------------------------------------------------------------------------------
TO COMPLETE THE WHOLE BUILDING PROJECT WE STILL NEED TO RAISE FUNDING

CAN YOU HELP – RAISE THE BAR

GO TO THE FOLLOWING LINK TO FIND OUT MORE

OR
WHY NOT JOIN "THE FRIENDS OF BOF"

GO TO - http://alturl.com/o2vqk TO FIND OUT MORE

Further reading