The steel frame and roof have had netting and scaffolding added to make them safe to commence the gutter installation and roof cladding next week.
We have now completed approximately 50% of the Brickwork and Blockwork up to underside of the Precast Concrete floor level, which is 1400mm above ground level
Fixing the Precast Concrete floor will commence next week, the precast beams will be placed and blocks will be placed in between the beams to form the floor, this will be insulated and a concrete slab poured with the new floor at approximately 1800 above ground level.
The Tuesday team of club members have now removed approximately 50% of the original timber clubhouse roof in preparation for the demolition works required to start Phase 2 in May 2017. The wood is being salvaged for re-use where possible.