News & EventsLatest NewsCalendar
20-05-2017 CLUB REDEVELOPMENT PROGRESS – UPDATE

20-05-2017 CLUB REDEVELOPMENT PROGRESS – UPDATE

Newark - ADMIN ONLY RUFC - WEB SITE21 May 2017 - 05:48
Share via
FacebookTwitter
https://www.newarkrugby.com/ne

PHASE 1 NEARS THE END – PHASE 2 READY TO GO!


PHASE 1 WORK

Blockwork Complete

After 6 weeks of hard graft the Block layers have finally completed all internal partitions and the final panel of external wall.

It proved a challenge with the building being 1.7 metre’s above ground level and some of the walls being 6 meters high above finished floor level, some blocks were handled up to 6 times by hand to get them up on to the internal scaffolding.

The joint between the top of the walls and the roof / steel will now be sealed for sound and fire protection.

The building will now be made secure with temporary doors.

The Joiner has started putting in timber joists for the ceilings, and also completed the ceiling space walkway to allow services installation to start in earnest from Monday 22nd .

The External black insulated cladding will be started next week from approx. 1m above ground to the eaves / gutter level.

Painting!

With the block walls completed we have started painting the internal walls to the changing rooms and toilet areas.

The remaining walls to the Corridor, 2 Referees rooms and Physio / First Aid will be painted next week.

The walls are being decorated before the Services (Plumbing and Electrics) are fixed.

Following some small amount of first fix air intake and extract ductwork, the Plumbing and Electrical First fix (pipes and wires) will start on Monday now the building is secure.

Follow on work in the next few weeks – tiling to showers, Fire stopping and sealing, Plasterboard Ceilings and more painting.

The end of Phase 1 is now in sight in approx. 8 to 9 weeks (end of July)

PHASE 2 WORK

Phase 2 update.

Following the tremendous effort by 31 of our members over 4 weeks, we have prepared Phase 2 site for CF Construction to start.

We met the Architect and Structural engineer last week, we now have confirmed plans and details and will start work w/c 22nd setting out the structure and starting the excavations for more concrete !!!

David

David Pick
David.pick@outlook.com or telephone 07713644668.

The Photo archive has been updated

Go to the following links to view the photo archive

PHASE 1

http://alturl.com/t8ofu

PHASE 2

http://alturl.com/xujre


TO COMPLETE THE WHOLE BUILDING PROJECT WE STILL NEED TO RAISE FUNDING

CAN YOU HELP - WHY NOT DONATE A BRICK

GO TO THE FOLLOWING LINK TO FIND OUT MORE

http://alturl.com/kx4ms



Further reading