Phase 2 Progress

Update on Phase 2.

Phase 2
Good progress continues.

All internal walls are now completed.

The Joinery team are in this week making the building secure at external window and door openings, followed by erecting the screen / partition which will be built between phase 2 and 3.

Gary Henderson, mini and youth parent, is due in with his team next week to paint the walls before the mechanical and electrical teams move in to run first fix cables and pipes.

This will be followed by doors and skirtings, vinyl flooring and suspended ceilings.

David

David Pick
David.pick@outlook.com or telephone 07713644668.

The Photo archive has been updated

Go to the following links to view the photo archive

PHASE 1

http://alturl.com/t8ofu

PHASE 2

http://alturl.com/xujre


-----------------------------
TO COMPLETE THE WHOLE BUILDING PROJECT WE STILL NEED TO RAISE FUNDING