MORE PROGRESS!.
Progress update.
The steel has arrived on site for the South (road end) entrance lobby and was erected today.
The bricklayers start the foundation brickwork from ground level to underside of floor level tomorrow.
This lobby building will include an entrance lobby, two toilets (yes more toilets) and a store room for furniture from the dining room when not being used (200 stackable chairs and 20 collapsible round tables.
The suspended ceiling contractors have started fixing their grid and the walls are plaster boarded.
The Timber Shiplap boarding to pitch 1 elevation has started and the rear existing wall (to pitch 2) is cleared ready for plastic coated steel cladding.
David
David Pick
David.pick@outlook.com or telephone 07713644668.
PHASE 1
http://alturl.com/t8ofu
PHASE 2
PHASE 3
http://alturl.com/obxdp
THE NEW SEASON WILL SOON BE HERE
IT IS IMPORTANT THAT THE CLUB CAN KEEP YOU UPDATED ON WHAT’S HAPPENING
HAVE YOU CHANGED YOUR EMAIL ADDRESS?
HAVE YOU CHECKED THAT YOUR EMAIL ADDRESS IS CORRECT ON THE CLUBS WEB SITE?
To change your Website email address, you need to follow the instructions in the following link
ARE YOU A MEMBER, PLAYER, PARENT, SUPPORTER, ETC ON THE CLUBS OFFICIAL WEB SITE?
KEEPING UPDATED WITH ALL THINGS RUGBY AT NEWARK
IF NOT SELECT “HOW TO JOIN” TO FIND OUT MORE
------------
.
.
.
.
.
.