Another good week.
The access Lift was installed on the rear (pitch 2) elevation on Tuesday, giving access from ground level to floor level.
The bricklayers started on Tuesday and by Friday evening all the foundation walls to underside of floor level were installed.
The Precast floor is due for delivery w/c 14th May.
The flood grille openings are being cut.
The supporting steel frame was installed ready for the movable wall.
David
David Pick
David.pick@outlook.com or telephone 07713644668.
PHASE 1
http://alturl.com/t8ofu
PHASE 2
PHASE 3
http://alturl.com/obxdp
--------------------------------------------
HAVE YOU VOLUNTEERED TO HELP AT THE NEWARK & NOTTINGHAMSHIRE COUNTY SHOW
IF NOT PLEASE DO IT NOW - YOU ARE NEEDED
FOR MORE DETAILS GO TO:- NEWARK SHOW
------------------------------------------------------------
ARE YOU A MEMBER OF THE CLUBS OFFICIAL WEB SITE?
KEEPING UPDATED WITH ALL THINGS RUGBY AT NEWARK
IF NOT SELECT “HOW TO JOIN” TO FIND OUT MORE
YOU CAN STILL HAVE A LITTLE TIME LEFT TO DONATE TO OBTAIN A SPECIAL BRICK
THAT WILL BE PART OF THE NEW CLUB HOUSE
SELECT “DONATE A BRICK” FOR MORE INFORMATION
---------------------------------------------------------
CAN YOU HELP – RAISE THE BAR
GO TO THE FOLLOWING LINK TO FIND OUT MORE
If you have any ideas of ways to help us please contact our president -'president@newarkrugby.com' who will be pleased to hear from you.
------------
.
.
.
.
.
.