C.F. Construction have now got all the Timber floor out, that’s the 1964 original clubhouse floor and the floor from the 1970s extension all down to ground level.
They have also got 30% of the pcc beams out.
Foundation excavation will start later this week.
David
David Pick
David.pick@outlook.com or telephone 07713644668.
PHASE 1
http://alturl.com/t8ofu
PHASE 2
PHASE 3
http://alturl.com/obxdp
--------------------------------------------
HAVE YOU VOLUNTEERED TO HELP AT THE NEWARK & NOTTINGHAMSHIRE COUNTY SHOW
IF NOT PLEASE DO IT NOW
FOR MORE DETAILS GO TO:- NEWARK SHOW
------------------------------------------------------------
ARE YOU A MEMBER OF THE CLUBS OFFICIAL WEB SITE?
KEEPING UPDATED WITH ALL THINGS RUGBY AT NEWARK
IF NOT SELECT “HOW TO JOIN” TO FIND OUT MORE
YOU CAN STILL HAVE A LITTLE TIME LEFT TO DONATE TO OBTAIN A SPECIAL BRICK
THAT WILL BE PART OF THE NEW CLUB HOUSE
SELECT “DONATE A BRICK” FOR MORE INFORMATION
---------------------------------------------------------
CAN YOU HELP – RAISE THE BAR
GO TO THE FOLLOWING LINK TO FIND OUT MORE
If you have any ideas of ways to help us please contact our president -'president@newarkrugby.com' who will be pleased to hear from you.
------------
.
.
.
.
.
.